PROJECT DESCRIPTION
Project comprises of:- Civil, Electro Mechanical, Under Ground Infra Structure, Roads & Fabrication, Complete Turnkey Construction includes Tasting & Commissioning. Construction of Automated Warehouse & Robotic Building Manufacture by Schafer (Germany)
Cost Polypropylene (CPP) 1 & 2, Machine manufactures are:- 1- W & H (windmöller & hölscher ) 2- Reifenhäuser. Biaxially-Oriented Polypropylene (BOPP) Machines Manufacturers are:- 1- Bruckner 2- Dornier. Shaded car parking, New carpeting workshop, Driver waiting room, Guard room, Chemical storage area, Site development, Potable water tanks and pumps foundations, CPP & Main Plant Production Building (Line 4), Silo foundations.
Excavation, Backfilling, Concrete works (Substructure, Basements, Super structure), water proofing, Masonry and Installation of Pre-engineered buildings including doors windows, Internal and External finishes.
Site development including Asphalt concrete pavements, Road side walkways pavements, Security internal fence, Utilities including portable water pipe line and irrigation systems, drainage system installation.
- Client: GPIL
- Location:
- Amount: 98,500,000 SAR
- Completion Date: June - 2023
LIVE PREVIEW